Project Overview

The Whorlton Suspension Bridge is a Grade-II listed structure and a scheduled monument (Historic England) and is one of the UK’s oldest road suspension bridges with the deck totally supported by its original chains.

In 2019, an inspection forced the bridge to be closed to all vehicles to allow further investigations into the cause of reported damage to the bridge.

At the end of 2020, the bridge was closed to all users due to public safety .

The rehabilitation project involves the whole suspension and deck structure being removed, refurbished and re-erected. As of December 2024, all components have been carefully removed and placed in storage for testing and refurbishment.

Our Role

VolkerLaser is currently working on behalf of Durham County Council to carry out structural rehabilitation works to the bridge.

CaSE has been awarded several scopes for the design and checking of temporary works and continues to support VolkerLaser in the delivery of this project.​

Location
England, UK
Project Value
£5.8M (rehabilitation)
Contractor
VolkerLaser
Contact Us
/ 03

Case Staff

/ 04

Services

  • Design of Cable crane
  • Design of catenary system
    (British Telecom Diversion)
  • Design of Working platforms
  • Retaining wall checks
  • Anchorages assessment
  • Develop Dismantling / Assembly sequence